|
Healthcare Facility Planning Tools and Guidelines |
|
|
Case Study |
|
SpaceMed Newsletter Print (PDF) Winter 2008 Volume 1, Number 1
Planning an Ambulatory Care
Facility: The Lean Toyota or the BACKGROUND Prudent Health System (PHS) planned to construct a new outpatient building to provide space for urgent care, ambulatory surgery, and various hospital-sponsored clinics on its main hospital campus. Space was needed to accommodate the following ten-year workload projections and corresponding clinical services:
In addition, a small express testing area was planned to consolidate routine, quick turnaround outpatient testing in a single area ― including X-ray, EKG, and specimen collection ― along with a small satellite laboratory. A room-by-room space program was prepared based on the projected workload and other functional planning assumptions provided by PHS ambulatory care staff. An initial schematic drawing was developed by the design architect and the project cost was estimated. A business plan was then prepared along with a financial pro forma analysis. Due to the large amount of space programmed and corresponding high project cost, and high operational costs relative to the projected incremental revenue, PHS’s Chief Financial Officer asked the executive team whether they really needed a “Hummer” when a “Toyota” might suffice. The executive team agreed to evaluate the impact on overall space need (and resulting capital and operational costs) of planning a “lean” facility versus a more “generous” facility. PLANNING APPROACH The executive team reviewed the original operational assumptions documented in the functional program. In conjunction with the facility planning consultant, they identified several key factors that could reduce the overall size and cost of the new outpatient facility:
COMPARISON OF FACILITY PLANNING ASSUMPTIONS A summary of the assumptions used for the lean versus the more generous space planning approach is shown below:
COMPARISON OF SPACE NEED The resulting space need is summarized in the following table based on the actual room-by-room space programs. In the lean scenario, 40,000 BGSF less space is required to accommodate the same projected annual workload.
CONCLUSION With 40,000 BGSF less space required in the lean scenario ― to accommodate the same projected annual workload ― the estimated project cost would be significantly reduced, particularly since the new space program can be accommodated with only two floors versus four as originally planned.
The PHS executive team eventually decided to construct the smaller, lean facility which would also be less costly to operate over time than the more generous facility. Moreover, the cost savings allowed the building to be designed to facilitate future horizontal as well as vertical expansion as required. back to top Cynthia Hayward Case Study 1308.1.1 |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Copyright ©2008 SpaceMed. All rights reserved.